Topic
What curriculum decisions do to funding
Curriculum teams make funding decisions every week without calling them that. This module connects each decision to the data it creates and the money it moves.
Enough detail to do the job and hold a sensible conversation with MIS or Finance.
- Official requirement: Stated by the official funding document named in the sources for this page.
- FEFunding explanation: Our plain-English explanation. Helpful, but the official document is the rule.
- Worked example: An illustration of how the rule applies in one situation. Not a universal rule.
- Recommended good practice: Operational advice from FEFunding. Not itself a funding requirement.
The decisions that move money
Aim choice decides whether an aim is fundable at all for the stream and the learner. Planned hours decide the funding band for 16 to 19 students, which sets the rate for the whole year. Leaver reporting decides how much funding is claimed for someone who has gone, and whether the aim sits in the achievement rate. Results reporting decides whether an aim counts as an achievement or as a non-achievement.
None of those is a data entry task. They are all curriculum decisions that happen to be recorded by somebody else.
A 16 to 19 student's funding band is determined by their planned hours for the year, which is the total of planned qualification hours and other planned, timetabled, education-related activity.
When a withdrawal is recorded changes both the funding earned and whether the aim counts in the achievement rate. Recording a withdrawal late is not a neutral administrative delay.
Aim eligibility is an attribute of the learning aim reference on the learning aims database, scoped by stream and by date. An aim that is not fundable for the stream produces a valid ILR record that generates nothing.
Planned hours comprise planned learning hours and planned employability, enrichment and pastoral hours, and determine the funding band and therefore the national funding rate applied for the year. Hours must be planned, timetabled, education-related and evidenced.
Actual end date, completion status and outcome drive both the funding period and the qualification achievement rate, and are the fields most often populated late.
CompStatus values cover continuing, completed, withdrawn and temporarily withdrawn. Outcome is recorded separately alongside OutcomeDate and, where applicable, an achievement date, and feeds the qualification achievement rate.
LearnPlanEndDate is set at enrolment from the planned programme. LearnActEndDate is populated only when the aim completes or the learner withdraws, and drives the funding period, the completion status and the performance calculation.
What to tell MIS, and when
MIS can only record what it is told. The two things worth being fast about are leavers and results.
- A leaver: within days, with the real last date of attendance.
- A result: as soon as it is known, not at the end of term.
- A timetable change that alters hours: before the next return.
- A learner who has moved onto a different aim: immediately.
The date matters as much as the fact. A withdrawal recorded with the date it was noticed rather than the date the learner stopped attending overstates funding and can put the aim in the wrong achievement cohort.
Results held back to be entered as a batch are the single largest cause of unrecorded outcomes, because the batch is often never completed before the year closes.
When a withdrawal is recorded changes both the funding earned and whether the aim counts in the achievement rate. Recording a withdrawal late is not a neutral administrative delay.
Set a notification service level in working days and measure against it. Report the number of withdrawals whose actual end date precedes the notification date by more than the agreed window, by curriculum area.
That single measure converts an abstract data-quality conversation into an operational one with a named owner.
Planning a programme with funding in mind
Thinking about funding when you design a programme is legitimate. Recording something that did not happen is not. The line between them is simple: is it real?
Designing a fuller programme, with more genuinely planned and timetabled activity, is good curriculum practice and it happens to attract more funding. Nobody should feel uncomfortable about that.
What is not legitimate is recording hours that are not delivered, counting activity that does not meet the conditions in the rules, or choosing a funding model because of what it pays rather than because it describes the provision.
The practical test is whether the plan would survive a reconciliation against the delivered timetable. If it would, it is a curriculum decision with a funding consequence. If it would not, it is a funding decision dressed as a curriculum one, and it will be found.
The same test applies to aims. Checking that an aim is fundable for the stream and the dates before it goes into the offer is planning. Discovering it in November is an avoidable cost.
A 16 to 19 student's funding band is determined by their planned hours for the year, which is the total of planned qualification hours and other planned, timetabled, education-related activity.
Evidence is strongest when it is created at the time of the event it describes and is retrievable without reconstruction. Evidence assembled after a query is asked is weaker and takes longer to produce.
Build two checks into the curriculum planning cycle: aim funding attributes confirmed on the learning aims database before the offer is published, and planned hours derived from the timetabling system rather than from a programme template.
Both are cheap at planning time and expensive at any other point in the year.
Worked examples
Worked example
A timetable change in November
An enrichment session that formed part of planned hours for a group of 16 to 19 students is withdrawn in November. Nobody updates the planned hours.
- The data. Planned hours on the ILR still include the withdrawn activity.
- The funding. Students may be recorded in a higher band than their delivered hours support.
- The evidence. The timetable no longer reconciles to the recorded hours.
- The audit test. Planned hours against delivered timetable is a standard test, and the reconciliation will fail.
A routine timetable change became a funding exposure because the hours were never revisited.
Whether the band actually changes depends on where the students sit relative to the band thresholds for the year.
Common pitfalls
Planned hours entered from a template
What goes wrong: Every learner on a programme is given the same hours figure regardless of what is timetabled for them.
Consequence: Hours cannot be reconciled to the delivered timetable, which is exactly what an audit tests.
Prevention: Derive planned hours from the timetabling system and reconcile annually before the December return.
Batching results until the end of term
What goes wrong: Results are collected and entered in bulk, and the bulk entry is not completed.
Consequence: Aims end with no outcome and count as non-achievements, permanently.
Prevention: Record outcomes as they become known, with a named owner per results window.
What this means for your role
Curriculum manager or head of department
Four of your routine decisions are the largest drivers of funding accuracy in the college.
- Report leavers within days, with the real last date of attendance.
- Record results as they arrive.
- Check planned hours against your actual timetable at the start of the year and after any change.
- Check new aims are fundable before they go into the offer.
See it play out
Scenario
An enrichment session is cancelled in November
A weekly enrichment session counted in planned hours is withdrawn after half term. Nobody thinks of it as a funding decision.
Work through itScenario
A student needs maths but nothing shows it
A 16 to 19 student without a qualifying maths grade is studying maths, but the record does not show it.
Work through itScenario
A qualification is withdrawn part way through the year
A qualification the college is delivering stops being available for new starts. Existing learners continue, new ones cannot.
Work through itSources
These are the official documents this page rests on. Where a figure, a deadline or an exact rule matters, the document is the authority and this page is the explanation.
Content reused from GOV.UK is Crown copyright, used under the Open Government Licence. FEFunding is not endorsed by the Department for Education.